Tile Roof Replacement in Burbank Hills from $8,000. Sound tile over failed underlayment is the commonest finding on a valley tile roof, and it is a relay, not a replacement. Free inspection and a written quote.
Tile is a Class A covering, but in a fire zone it is the assembly that is rated, not the tile on its own. What matters up here is what is under and behind it: the underlayment, and whether the open ends at the eave and ridge are blocked against ember entry. A tile roof with open birdstops is a tile roof with a way in.
Concrete and clay tile outlives the underlayment beneath it by decades. A tile field that looks perfectly sound from the street can be sitting on felt that has gone brittle and torn, which is why the leak appears with no visible broken tile anywhere near it.



Full tile replacement in Los Angeles runs $15 to $25 per square foot, so $30,000 to $60,000 is a normal figure for one. A lift and relay -- your own tile back down over new underlayment -- is $8,000 to $22,000. That is the single biggest number on this site and it turns on one question: how much of your tile is still good. Two things push a hillside quote up. Access -- staging and material handling on a sloping lot with a narrow street. And, inside a Very High Fire Hazard Severity Zone, a Chapter 7A Class A assembly adds roughly $1 to $5 per square foot, about 22%. Worth knowing before comparing two quotes that are not specifying the same roof.
If the tile is sound and only the felt beneath has failed, the relay is the right job at roughly half the cost. We count the salvageable tile before quoting either.
Spalling or widely broken tile, an obsolete profile with no match available, clay rather than concrete, or framing that needs attention once the weight comes off.
Whether the tile itself needed replacing at all. Ask what is wrong with the tile, specifically, and if the answer is about the felt underneath it then you are being quoted the wrong job.
Two things change up here. Access -- staging, material handling and dumpster placement are all harder on a sloping lot with a narrow street. And fire. Parts of the Burbank hillside sit in a Very High Fire Hazard Severity Zone, and inside one a re-roof is a Class A assembly under Chapter 7A rather than a choice of product. We will not tell you your parcel is in one; the state and the city both publish maps and your own address is the only one that matters.
The state fire marshal publishes a Very High Fire Hazard Severity Zone map for Burbank, and the city publishes its own Mountain Fire Zone map. Check your own parcel on both rather than taking a contractor's word for it.
This is a replacement company saying so, which is the point. The most expensive mistake in this market is buying the whole roof when the job was a section of it.
A ridge cap loosened in a Santa Ana, an upstand split by movement, a vent boot gone brittle in the heat. Repairs, all of them, in the hundreds -- and all of them regularly offered as proof that the whole roof has had it.
A separate garage, an outbuilding, a rear addition on its own roof, or one slope that failed years ahead of the others. What we will also tell you is when a partial is just a deposit on doing the rest at a second mobilization cost.
When it is, we will say so plainly, because that is the same job as saying the opposite done honestly. What no homeowner should accept is either verdict without being walked through the reasoning.
On the hillside the replacement decision runs into the fire decision.
Wind is the local variable on the hillside.
Split-level hillside houses are joined by short low-slope links between the levels, and those links are where the trouble is.
The multi-unit stock up here is condominium clusters on sloping sites, which means a board, a reserve study and a shared roof over separately owned units.
This is where the partial-versus-full decision has a genuine code cost.
Laid out 1887. Mixed-era streets, often three roofs a lot.
A 1945-50 grid, and a garage roof out the back.
Studio quarter. Controlled parking, managed loading.
Horse country. Outbuildings, and Griffith Park litter.
Half lots. All junction, no side yard.
Heavy canopy, high tile share, LADBS permits.
Dense. Small apartment blocks and LADBS permits.
What is worth knowing before you book this.
It might be the right price for the wrong job. Full tile replacement in Los Angeles is $15 to $25 per square foot, so $30,000 to $60,000 is normal for one. But many tile roofs here need a lift and relay instead -- $8,000 to $22,000, because your existing tile goes back down.
Because the leak is under it. Concrete and clay tile outlast the felt beneath them by decades, so the underlayment tears and goes brittle while the tile field above still looks new from the street. That is the commonest tile failure we see and it is not visible from the ground.
Maybe, but get a second opinion before you sign anything, and never accept a price given at the door. Ask for a CSLB C-39 number and check it on the public register. That takes a minute and it is the single most effective thing you can do.
A typical single-family Burbank house is a three to five day job once it starts: tear-off and dry-in first, covering after. Tile takes longer than composition, and a lift and relay longer again because the tile is handled twice. Weather moves it, and we will not dry-in a roof we cannot finish.
No. The inspection is free, the written quote is free, and there is no obligation attached to either. What we will not do is give you a price at the door without going up.
Free inspection, and a written quote against a written scope. Every slope photographed before and after - the set is yours.